Installation & Commissioning Of Pipe Coating Plant
Mashhad 1999 – 2001
EmployerMAPNA.
Consultant
Main contractor Tanavob
Quantity
Concrete M3
Structure Fabrication Ton
Structure Installation Ton
Equipment Installation Ton 8,130
Welding ID 84,156
Cabling M 249,108
Field Instrument Set 872
Description
This project consists of installation of three units siemens turbine and generator their capacity 330 MW and balance of plant including HVAC, compressed air, water treatment plant, diesel generator , 02 injection, ear thing, lightening, telephone ,paging, related tests and precommissioning